A project with a CPI of .92 would be: A) Under Budget B) Behind Schedule C) Ahead of Schedule D) Over Budget This week’s correct answer is: D “The cost performance index (CPI) is a measure of the cost efficiency …
Month: January 2020
Project life cycles in which the project scope, time, and cost are determined in the early phases of the project are known as: A) Iterative B) Predictive C) Hybrid D) Incremental This week’s correct answer is: B “In a predictive …
The amount of time that a schedule activity can be delayed without delaying the early start of any successor activity is termed: A) Total Float B) Total Slack C) Free Float D) Free Time This week’s correct answer is: …
A project team examining data to determine whether or not a process is stable or has predictable performance is likely using what Quality Management tool? A) Control Chart B) Scatter Diagram C) Histogram D) Affinity Diagram This week’s correct …